Touring (Travelling) Cinemas

I. Procedure for obtaining Electrical Certificate (Form - 'D') for New Touring Theatres

  • The Applicant (Cinema Owner) after obtaining No Objection Certificate in Form - 'B' from the Licensing Authority (District Collector or Commissioner of Police as the case may be) shall forward the following to the concerned Divisional Electrical Inspector.
    • Questionnaire Form for Touring Cinema, duly filled in.
    • Completion Report in Std. Form obtained from the Electrical Contractor who erected the electrical installation
    • Copy of Appointment Orders issued to Cinema Operator(s), and Electrician / Wireman having valid licence
    • Consent letters of the Cinema Operator(s) and Electrician / Wireman appointed
    • Original remittance challan for Rs. 400/ - paid in to a Govt. treasury under this dept. head of account.
    • Purchase Bills or Sale Deed or Lease Agreement for the Cinema equipments (Projector, Slide Projector, Rectifier, etc.,) and Fire Extinguishers
    • Test Certificate in original for the fire extinguishers.
    • Copy of No Objection Certificate issued by the Licensing Authority
    • On receipt of the above in complete shape, Inspection of the Cinema will be arranged and Defects report issued (for any defects found during inspection of Cinema) within 7 days from the date of inspection.
    • The Applicant on receipt of the defects report shall arrange to rectify all the defects and send an item wise rectification report to the Electrical Inspector. (The defects of electrical nature are to be rectified by an electrical contractor holding valid licence and the item wise rectification report obtained from him should be forwarded)
    • If the rectification report is in order, the Electrical Certificate in form - 'D' (valid for 1 year) will be issued to the applicant.